This school in Plymouth, Devon was looking for a groundworks contractor to form a new entrance after having some building work carried out inside.

After a brief discussion, they detailed what they proposed. D.Hall Plant Hire & Groundworks measured the area and provided them with a detailed quote.

The job consisted of the following.

Removal of green waste from the site to a licenced facility

Excavation of subsoil to a licenced facility

Concrete back edgers laid on Gen2 Concrete and haunced

Importation of .150mm of 803 type 1 sub-base and compacted in place

x1 layer of A252 reinforcing mesh

.150mm of C35 concrete with a brushed finish

Have a look at the Concrete Foothpath after finishing the groundworks in Plymouth.

The original content is published on dhallplant

This post was created with our nice and easy submission form. Create your post!

What do you think?

Dog Breeder in Russell MA

What Tools Do Professional Groomers Recommend to Dog Breeders?

close up pen magnifying glass document 1048944 30642376 4

Sodium Chlorate Market Size and Share Analysis: Projections to 2031